PROJECT:                   Renovation and extension of MFH Jona

BUILDING VOLUME:          650,000 CHF

OUR TASK:   Project and construction management

RESPONSIBLE:                Rene Todorov

​

January 2023 -- scheduled start of renovation
February 2023 -- Building gutting
April 2023 -- Excavation for cultivation
May 2023 -- Builder
June 2023 -- Roof conversion
July 2023 -- Installation of subfloor
August 2023 -- Completion of shell construction and windows
September 2023 -- Interior work
October 2023 - Completion